Completed Projects 2000-2006
|
PROJECT: Upgrade Intrusion Detection System LOCATION: Air National Guard Base, South Portland, Maine TYPE: Upgrade existing systems OWNER: Air National Guard ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $18,184 START DATE OF PROJECT: September 2006 SCHEDULE OF COMPLETION: December 2006 PERCENT WORK WITH OWN FORCES: 10% PROJECT MANAGER: Stacey Morrison SUPERINTENDENT: Stacey Morrison CONTACT: MSgt Patrick Nott, 207-990-7419 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor |
PROJECT: Building 417 Vestibule LOCATION: Air National Guard Base, Bangor, Maine TYPE: New storefront system OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $17,111 START DATE OF PROJECT: September 2006 SCHEDULE OF COMPLETION: January 2007 PERCENT WORK WITH OWN FORCES: 10% PROJECT MANAGER: Stacey Morrison SUPERINTENDENT: Steve Dumais CONTACT: MSgt Patrick Nott, 207-990-7419 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor |
|
PROJECT: Penobscot Valley Hospital Lobby Renovation LOCATION: Lincoln, Maine TYPE: Interior Renovations OWNER: Penobscot Valley Hospital ARCHITECT: SMRT, Lynne Holler CONTRACT AMOUNT: $295,020 START DATE OF PROJECT: September 2006 SCHEDULE OF COMPLETION: December 2006 PERCENT WORK WITH OWN FORCES: 20% PROJECT MANAGER: Fred Gay SUPERINTENDENT: Bruce Clement CONTACT: Paul Smith, 207-794-3321 PROJECT DELIVERY METHOD: Bid, General Contractor |
PROJECT: New Mobile Office Setup and Installation LOCATION: Hodgdon, Maine TYPE: Sitework for mobile office along with utilities and wiring OWNER: U.S. General Services Administration ARCHITECT: GSA CONTRACT AMOUNT: $85,010 START DATE OF PROJECT: September 2006 SCHEDULE OF COMPLETION: October 2006 PERCENT WORK WITH OWN FORCES: 15% PROJECT MANAGER: Emelie Ferland SUPERINTENDENT: Emelie Ferland CONTACT: Laurence Albright, 207-532-7852 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
|
PROJECT: Roof Replacement Building #488 LOCATION: Air National Guard Base, Bangor, Maine TYPE: Replace Existing Roof Building #488 OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $27,840 START DATE OF PROJECT: June 2006 SCHEDULE OF COMPLETION: August 2006 PERCENT WORK WITH OWN FORCES: 15% PROJECT MANAGER: Stacey Morrison SUPERINTENDENT: Steve Dumais CONTACT: MSgt Patrick Nott, 207-990-7419 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
PROJECT: Tank Repairs/Inspections LOCATION: Air National Guard Base, Bangor, Maine TYPE: Tank Repair & Inspect/Test Leak & Protection Systems OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $62,289 START DATE OF PROJECT: May 2006 SCHEDULE OF COMPLETION: August 2006 PERCENT WORK WITH OWN FORCES: 5% PROJECT MANAGER: Emelie Ferland SUPERINTENDENT: Steve Dumais CONTACT: MSgt Treena Nadeau 207-990-7353 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor |
|
PROJECT: Demolition / Repair of Building # 515 LOCATION: Air National Guard Base, Bangor, Maine TYPE: Demolition / Repair Existing Building OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $387,697 START DATE OF PROJECT: April 2006 SCHEDULE OF COMPLETION: October 2006 PERCENT WORK WITH OWN FORCES: 15% PROJECT MANAGER: Michael Lemieux SUPERINTENDENT: Steve Dumais CONTACT: SMSgt Neils Neilson, 207-990-7016 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
PROJECT: Upgrade Building #510 Fire Alarm Systems LOCATION: Air National Guard Base, Bangor, Maine TYPE: Upgrade Fire Alarm Systems OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $62,030 START DATE OF PROJECT: June 2006 SCHEDULE OF COMPLETION: July 2006 PERCENT WORK WITH OWN FORCES: 15% PROJECT MANAGER: Stacey Morrison SUPERINTENDENT: Steve Dumais CONTACT: Darlene Howes 207-626-4550 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor |
|
PROJECT: EMCC – Maine Hall Renovations LOCATION: Bangor, Maine TYPE: Renovations to Existing Building OWNER: Eastern Maine Community College ARCHITECT: WBRC Architects-Engineers, Inc. CONTRACT AMOUNT: $1,529,572 PERCENT COMPLETE: 99% -Spring Work START DATE OF PROJECT: June, 2005 SCHEDULE OF COMPLETION: November 2006 PERCENT WORK WITH OWN FORCES: 20% PROJECT MANAGER: Michael Lemieux SUPERINTENDENT: Lou Turmelle CONTACT: Dan Belyea, Director of Facilities Management PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Aubert Hall – Room 231 Renovations LOCATION: Orono, Maine TYPE: Renovations to Aubert Hall OWNER: University of Maine System ARCHITECT: Symmes, Maini & McKee Associates CONTRACT AMOUNT: $1,052,740 PERCENT COMPLETE: 95%- Change Order and Spring Work START DATE OF PROJECT: June 2005 SCHEDULE OF COMPLETION: December 2005 PERCENT WORK WITH OWN FORCES: 99% PROJECT MANAGER: Michael Lemieux SUPERINTENDENT: Tony Savage CONTACT: Fred Stoddard, Building Construction Engineer PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: DFD Russell Medical Center LOCATION: Leeds, Maine TYPE: Addition / Renovations to Medical Offices OWNER: DFD Russell Medical Center ARCHITECT: Harriman Associates CONTRACT AMOUNT: $566,185 PERCENT COMPLETE: 99% -Spring Work START DATE OF PROJECT: April 2005 SCHEDULE OF COMPLETION: December 2005 PERCENT WORK WITH OWN FORCES: 99% -Spring Work PROJECT MANAGER: Richard Leeman SUPERINTENDENT: Will Ryder CONTACT: Laurie Kane, CEO PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Corundel Commons LOCATION: Corinna, Maine TYPE: New Senior Housing Facility OWNER: Corundel Commons Senior Housing Associates LP ARCHITECT: Salmon Falls Architecture CONTRACT AMOUNT: $1,639,105 PERCENT COMPLETE: 95% START DATE OF PROJECT: February 2005 SCHEDULE OF COMPLETION: April 2006 PERCENT WORK WITH OWN FORCES: 98% PROJECT MANAGER: Richard Leeman SUPERINTENDENT: Kirk Wood CONTACT: Joe Ponzetti PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Topsham Rental Center LOCATION: Topsham, Maine TYPE: Pre-Engineered Steel Building OWNER: Terrance Gray ARCHITECT: N/A CONTRACT AMOUNT: $503,350 PERCENT COMPLETE: 99% START DATE OF PROJECT: September, 2005 SCHEDULE OF COMPLETION: February, 2006 PERCENT WORK WITH OWN FORCES: 53% PROJECT MANAGER: Larry Rancourt SUPERINTENDENT: Jim Savage CONTACT: Terrance Gray PROJECT DELIVERY METHOD: Negotiated
|
PROJECT: DDC Controls LOCATION: Air National Guard Base, Bangor, Maine TYPE: Mechanical systems upgrade OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $233,007.00 PERCENT COMPLETE: 98% START DATE OF PROJECT: August 2005 SCHEDULE OF COMPLETION: October 2005 PERCENT WORK WITH OWN FORCES: 11% PROJECT MANAGER & SUPERINTENDENT: Emelie Ferland CONTACT: Robert Busch 207-990-7419 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
|
PROJECT: USM Childcare Facility LOCATION: Gorham, Maine TYPE: Construction of New Facility OWNER: University of Maine System ARCHITECT: TFH Architects Chris Briley 207-775-6141 CONTRACT AMOUNT: $1,617,372 PERCENT COMPLETE: 95% START DATE OF PROJECT: November 2005 SCHEDULE OF COMPLETION: June 2006 PERCENT WORK WITH OWN FORCES: 40% PROJECT MANAGER: Mike Lemieux SUPERINTENDENT: Tony Savage CONTACT: Dana Gray 207-780-5646 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: UMA Student Center Roof Improvements LOCATION: Augusta, Maine TYPE: Roof and Entrance Improvements OWNER: University of Maine System ARCHITECT: WBRC CONTRACT AMOUNT: $237,764 PERCENT COMPLETE: 95% START DATE OF PROJECT: November, 2005 SCHEDULE OF COMPLETION: February, 2006 PERCENT WORK WITH OWN FORCES: 40% PROJECT MANAGER: Richard Leeman SUPERINTENDENT: Richard Beaulieu CONTACT: Peter St. Michael PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: DEP Ray Building LOCATION: Augusta, Maine TYPE: Renovation of Main Lobby and Bathrooms Floors 1-3 OWNER: Bureau of General Services, State of Maine ARCHITECT: Cubellis Associates CONTRACT AMOUNT: $328,486 PERCENT COMPLETE: 24% START DATE OF PROJECT: January, 2006 SCHEDULE OF COMPLETION: April, 2006 PERCENT WORK WITH OWN FORCES: 60% PROJECT MANAGER: Mike Lemieux SUPERINTENDENT: Bruce Clement CONTACT: Julie Tupper PROJECT DELIVERY METHOD: Bid, General Contractor |
PROJECT: Bangor City Hall Renovations LOCATION: Bangor, Maine TYPE: Basement Renovations OWNER: City of Bangor ARCHITECT: Carpenter Associates CONTRACT AMOUNT: $167,500 PERCENT COMPLETE: 30% START DATE OF PROJECT: February, 2006 SCHEDULE OF COMPLETION: April, 2006 PERCENT WORK WITH OWN FORCES: 30% PROJECT MANAGER: Richard Leeman SUPERINTENDENT: Steve Dumais CONTACT: Jeff Landwehr PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Canopy over Truck Inspection Platform LOCATION: Air National Guard Base, Bangor, Maine TYPE: Pre-engineered canopy OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $54,111.00 START DATE OF PROJECT: October 2005 SCHEDULE OF COMPLETION: November 2005 PERCENT WORK WITH OWN FORCES: 78% PROJECT MANAGER: Emelie Ferland SUPERINTENDENT: Dick Beaulieu CONTACT: Sgt. Dirck Storms 207-990-7434 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
PROJECT: Maine Veteran’s Home Addition/Downeast Community Hospital LOCATION: Machias, Maine OWNER: Maine Veteran’s Home ARCHITECT: SMRT CONTRACT AMOUNT: $9,752,808 PERCENT COMPLETE: 99% START DATE OF PROJECT: May 2004 DATE OF COMPLETION: January 2006 PERCENT WORK WITH OWN FORCES: 99% -Spring Work PROJECT MANAGER: Larry Rancourt SUPERINTENDENT: Fred Gay CONTACT: Ron Herbert, MVH 207-763-6300 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Repairs to Curbs, Walkways, Stairs & Dead End Water Mains LOCATION: Air National Guard Base, Bangor, Maine TYPE: Site work OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $90,368.82 START DATE OF PROJECT: September 2005 SCHEDULE OF COMPLETION: November 2005 PERCENT WORK WITH OWN FORCES: 45% PROJECT MANAGER: Larry Rancourt SUPERINTENDENT: Dick Beaulieu CONTACT: Mrs. Darlene R. Howes 207-626-4559 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
PROJECT: New Portland Glass Facility LOCATION: Brunswick, Maine TYPE: Construction of Retail Facility OWNER: The Dwyer Group, Inc. ARCHITECT: James Herrick CONTRACT AMOUNT: $1,150,000 START DATE OF PROJECT: May 2005 SCHEDULE OF COMPLETION: October 2005 PERCENT WORK WITH OWN FORCES: 15% PROJECT MANAGER: Richard Leeman SUPERINTENDENT: Charlie O’Brien CONTACT: Mike Bidwell PROJECT DELIVERY METHOD: Negotiated
|
|
PROJECT: Blue Hill Wreaths LOCATION: Blue Hill, Maine TYPE: Pre-Engineered Steel Building OWNER: Terrance Gray ARCHITECT: N/A CONTRACT AMOUNT: $130,854 START DATE OF PROJECT: July, 2005 SCHEDULE OF COMPLETION: September, 2005 PERCENT WORK WITH OWN FORCES: 100% PROJECT MANAGER: Larry Rancourt SUPERINTENDENT: Jim Savage CONTACT: Terrance Gray PROJECT DELIVERY METHOD: Negotiated
|
PROJECT: Library Expansion Project LOCATION: Lewiston, Maine TYPE: Phase III Renovations OWNER: City of Lewiston ARCHITECT: Schwartz/Silver Architects, Inc. CONTRACT AMOUNT: $2,830,123 START DATE OF PROJECT: March 2004 SCHEDULE OF COMPLETION: September 2005 PERCENT WORK WITH OWN FORCES: 20% PROJECT MANAGER: Michael Lemieux SUPERINTENDENT: Richard Beaulieu CONTACT: Available upon request PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Bucksport Regional Health Center LOCATION: Bucksport, Maine TYPE: Renovations of entrance and nurse’s station OWNER: Bucksport Regional Health Center ARCHITECT: Ames Engineers CONTRACT AMOUNT: $190,777 START DATE OF PROJECT: October 2004 SCHEDULE OF COMPLETION: February 2005 PERCENT WORK WITH OWN FORCES: 30% PROJECT MANAGER: Michael Lemieux SUPERINTENDENT: Will Ryder CONTACT: Jack Corrigan PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Fairground Apartments LOCATION: Orrington, Maine TYPE: Renovation to Apartment Complex OWNER: Orrington Housing Corp. ARCHITECT: Carpenter Associates CONTRACT AMOUNT: $155,179 START DATE OF PROJECT: February 2005 SCHEDULE OF COMPLETION: June 2005 PERCENT WORK WITH OWN FORCES: 63% PROJECT MANAGER: Donald McGilvery SUPERINTENDENT: Jim Savage CONTACT: Susanne Shaw PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Dr. Bossong & Dr. Rice Dental Offices LOCATION: Brunswick, Maine TYPE: New Medical Office Building OWNER: Dr. Lawrence Bossong and Dr. Thomas Rice ARCHITECT: Bethanis & Hayford CONTRACT AMOUNT: $1,128,511 PERCENT COMPLETE: 100% START DATE OF PROJECT: July, 2004 SCHEDULE OF COMPLETION: February, 2005 PERCENT WORK WITH OWN FORCES: 30% SUPERINTENDENT: Richard Beaulieu CONTACT: Available upon request PROJECT DELIVERY METHOD: Bid, General Contractor |
PROJECT: Reny’s Surgical Offices LOCATION: Damariscotta, Maine TYPE: Renovation of former Reny’s Warehouse OWNER: Renbro Inc. ARCHITECT: George Parker CONTRACT AMOUNT: $144,790 PERCENT COMPLETE: 5% START DATE OF PROJECT: September 2004 SCHEDULE OF COMPLETION: February 2005 PERCENT WORK WITH OWN FORCES: 50% SUPERINTENDENT: Kirk Wood CONTACT: John or Bob Reny 207-563-3177, George Parker 207-563-8754 PROJECT DELIVERY METHOD: Negotiated General Contract
|
|
PROJECT: Damariscotta Municipal Offices LOCATION: Damariscotta, Maine TYPE: Renovation of former School Building OWNER: Town of Damariscotta ARCHITECT: Pine Tree Engineering CONTRACT AMOUNT: $589,000 START DATE OF PROJECT: June 2004 SCHEDULE OF COMPLETION: December 2004 PERCENT WORK WITH OWN FORCES: 40% SUPERINTENDENT: Kirk Wood CONTACT: William S. Post, Administrator 207-563-5168 PROJECT DELIVERY METHOD: Bid, General Contractor |
PROJECT: Reny’s Therapist Offices LOCATION: Damariscotta, Maine TYPE: Renovation of former Reny’s Warehouse OWNER: Renbro Inc. ARCHITECT: George Parker CONTRACT AMOUNT: $122,064 START DATE OF PROJECT: October 2004 SCHEDULE OF COMPLETION: December 2004 PERCENT WORK WITH OWN FORCES: 50% SUPERINTENDENT: Kirk Wood CONTACT: John or Bob Reny 207-563-3177, George Parker 207-563-8754 PROJECT DELIVERY METHOD: Negotiated General Contract
|
|
PROJECT: Senator Inn Restaurant Renovations LOCATION: Augusta, Maine TYPE: Interior Renovations OWNER: Vern & Betsy Cook ARCHITECT: None CONTRACT AMOUNT: $150,000 START DATE OF PROJECT: August, 2004 SCHEDULE OF COMPLETION: November, 2004 PERCENT WORK WITH OWN FORCES: 40% SUPERINTENDENT: Will Ryder CONTACT: Available upon request PROJECT DELIVERY METHOD: Design/Builder, Negotiated Contract
|
PROJECT: Lambs Book & Bible Store LOCATION: Bangor, Maine TYPE: Renovations of former restaurant to retail space OWNER: Royce Cross ARCHITECT: Philip Dougherty, Renaissance Design CONTRACT AMOUNT: $125,000 START DATE OF PROJECT: September, 2004 SCHEDULE OF COMPLETION: November, 2004 PERCENT WORK WITH OWN FORCES: 30% SUPERINTENDENT: Don McGilvery CONTACT: Alice Dyer PROJECT DELIVERY METHOD: Negotiated, General Contractor
|
|
PROJECT: Precast Concrete Products of Maine Plant Expansion TYPE: Pre-engineered Building addition OWNER: Terrance Gray, President, PCM ARCHITECT: None CONTRACT AMOUNT: $250,000 START DATE OF PROJECT: July, 2004 SCHEDULE OF COMPLETION: November, 2004 PERCENT WORK WITH OWN FORCES: 90% SUPERINTENDENT: Jim Savage CONTACT: Available upon request PROJECT DELIVERY METHOD: Design/Builder, Negotiated Contract
|
PROJECT: Clark’s Garage LOCATION: Gardiner, Maine TYPE: Installation of Metal Building OWNER: Bob Clarke ARCHITECT: N/A CONTRACT AMOUNT: $31,283 START DATE OF PROJECT: October 2004 SCHEDULE OF COMPLETION: November 2004 PERCENT WORK WITH OWN FORCES: 100% SUPERINTENDENT: Jim Savage CONTACT: Available upon request PROJECT DELIVERY METHOD: Negotiated General Contract |
|
PROJECT: Comfort Inn Renovations III LOCATION: Augusta, Maine TYPE: Renovations of Guest Rooms OWNER: Augusta Civic LLC DBA ARCHITECT: N/A CONTRACT AMOUNT: $22,339 START DATE OF PROJECT: September, 2004 SCHEDULE OF COMPLETION: October, 2004 PERCENT WORK WITH OWN FORCES: 40% SUPERINTENDENT: Stacey Morrison CONTACT: Linette Searcy (207) 623-1000 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Capitol Shopping Center LOCATION: Augusta, Maine TYPE: Interior tenant fit-up OWNER: WP Realty ARCHITECT: Bunker & Savage CONTRACT AMOUNT: $321,133 START DATE OF PROJECT: March 2004 DATE OF COMPLETION: August 2004 PERCENT WORK WITH OWN FORCES: 50% SUPERINTENDENT: Tony Savage CONTACT: Available upon request PROJECT DELIVERY METHOD: Bid, General Contractor |
|
PROJECT: Reny’s Podiatrist Offices LOCATION: Damariscotta, Maine TYPE: Renovation of former Reny’s Warehouse OWNER: Renbro Inc. ARCHITECT: George Parker CONTRACT AMOUNT: $154,791 START DATE OF PROJECT: June 2004 SCHEDULE OF COMPLETION: August 2004 PERCENT WORK WITH OWN FORCES: 50% SUPERINTENDENT: Kirk Wood CONTACT: John or Bob Reny 207-563-3177, George Parker 207-563-8754 PROJECT DELIVERY METHOD: Negotiated General Contract |
PROJECT: Coastal Foot and Ankle LOCATION: Falmouth, Maine TYPE: Interior tenant fit-up OWNER: Dr. Meredith ARCHITECT: Gawron Turgeon Architects CONTRACT AMOUNT: $147,000 PERCENT COMPLETE: 90% START DATE OF PROJECT: January 2004 SCHEDULE OF COMPLETION: April 2004 PERCENT WORK WITH OWN FORCES: 20% SUPERINTENDENT: Richard Beaulieu CONTACT: Available upon request PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Dr. Bufo Tenant Fit-up LOCATION: U. S. Route 1, Scarborough, Maine TYPE: Interior tenant fit-up OWNER: Dr. Bufo ARCHITECT: Studio MNEMOSYNE CONTRACT AMOUNT: $190,000.00 START DATE OF PROJECT: January 2004 DATE OF COMPLETION: April 2004 PERCENT WORK WITH OWN FORCES: 30% SUPERINTENDENT: Richard Beaulieu CONTACT: Dr. Michael Bufo PROJECT DELIVERY METHOD: Design/Build
|
PROJECT: KeyBank Cash Vault LOCATION: Gorham, Maine TYPE: Renovate warehouse to OWNER: KeyBank ARCHITECT: VWCGS Architects CONTRACT AMOUNT: $370,129 START DATE OF PROJECT: January 2004 SCHEDULE OF COMPLETION: March 2004 PERCENT WORK WITH OWN FORCES: 35% SUPERINTENDENT: Fred Gay CONTACT: Patrick Hedderman, Property Manager (518) 257-8686 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Chad Little Outdoor Power Equipment LOCATION: Brunswick, Maine TYPE: Addition to existing equipment service sales and service building OWNER: Bruce Weeks ARCHITECT: Kirby Building Systems CONTRACT AMOUNT: $220,476 START DATE OF PROJECT: November 2003 SCHEDULE OF COMPLETION: Feb 2004 PERCENT WORK WITH OWN FORCES: 60% SUPERINTENDENT: Jimmy Savage CONTACT: Available upon request PROJECT DELIVERY METHOD: Design/Build
|
PROJECT: Hope Elementary School LOCATION: Hope, Maine TYPE: New addition and renovation of existing OWNER: Maine School Union 69 ARCHITECT: Woodard & Curran Inc. CONTRACT AMOUNT: $1,512,339.00 START DATE OF PROJECT: June 2003 SCHEDULE OF COMPLETION: Feb 2004 PERCENT WORK WITH OWN FORCES: 25% SUPERINTENDENT: Fred Gay CONTACT: Available upon request PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Senator Inn Spa Expansion LOCATION: Western Avenue, Augusta, Maine TYPE: Design/Build Services for a Three-story addition to existing Spa facility. OWNER: Vern & Betsey Cook ARCHITECT: Fuller Nichols Architects CONTRACT AMOUNT: Estimated: $900,000.00 START DATE OF PROJECT: December 2002 SCHEDULE OF COMPLETION: February 2004 PERCENT WORK WITH OWN FORCES: 25% SUPERINTENDENT: Ken Smith CONTACT: Vern Cook 207-622-8800 PROJECT DELIVERY METHOD: Design/Build
|
PROJECT: DDC Controls LOCATION: Air National Guard Base, Bangor, Maine TYPE: Mechanical systems upgrade. OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $182,482.00 START DATE OF PROJECT: October 2002 SCHEDULE OF COMPLETION: January 2004 PERCENT WORK WITH OWN FORCES: 10% SUPERINTENDENT: Stacey Morrison CONTACT: SGT Robert Busch 207-990-7419 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
|
PROJECT: Reny’s Doctors’ Offices LOCATION: Damariscotta, Maine TYPE: Renovation of former Reny’s Warehouse OWNER: Renbro Inc. ARCHITECT: George Parker CONTRACT AMOUNT: $280,729 START DATE OF PROJECT: November 2003 SCHEDULE OF COMPLETION: April 2004 PERCENT WORK WITH OWN FORCES: 50% SUPERINTENDENT: Kirk Wood CONTACT: John or Bob Reny 207-563-3177 George Parker 207-563-8754 PROJECT DELIVERY METHOD: Negotiated General Contract
|
PROJECT: Wright Pierce Roof Improvements LOCATION: Topsham, Maine TYPE: Addition of a new, pitched roof over existing building ARCHITECT: Wright Pierce Engineers CONTRACT AMOUNT: $107,200 START DATE OF PROJECT: October 2003 SCHEDULE OF COMPLETION: January 2004 PERCENT WORK WITH OWN FORCES: 10% SUPERINTENDENT: Jim Savage CONTACT: Daniel Pratt, Wright Pierce Engineers 207-865-6332 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
LOCATION: Air National Guard Base, Bangor, Maine TYPE: Fueling Area Improvements: 3 Metal Buildings and an Inspection Platform OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $168,049 START DATE OF PROJECT: October 2003 SCHEDULE OF COMPLETION: January 2004 PERCENT WORK WITH OWN FORCES: 70% SUPERINTENDENT: Richard Beaulieu CONTACT: SGT Robert Busch 207-990-7419 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
LOCATION: Air National Guard Base, South Portland, Maine TYPE: Mechanical systems upgrade, Building P-9 OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $74,715 START DATE OF PROJECT: November 2002 SCHEDULE OF COMPLETION: January 2004 PERCENT WORK WITH OWN FORCES: 2% SUPERINTENDENT: Stacey Morrison CONTACT: Darlene Rae Howes, Contract Specialist 207-626-4559 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
|
LOCATION: Air National Guard Base, South Portland, Maine TYPE: Roofing replacement, Building 8. OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $60,160 START DATE OF PROJECT: November 2003 SCHEDULE OF COMPLETION: January 2004 PERCENT WORK WITH OWN FORCES: 14% SUPERINTENDENT: Stacey Morrison CONTACT: Darlene Rae Howes, Contract Specialist 207-626-4559 PROJECT DELIVERY METHOD: Task Order Bid, General Contractor
|
PROJECT: Tri Sports LOCATION: Topsham, Maine TYPE: New storage building addition OWNER: Tri Sports ARCHITECT: Kirby Building Systems CONTRACT AMOUNT: $109,299 START DATE OF PROJECT: September 2003 SCHEDULE OF COMPLETION: November 2003 PERCENT WORK WITH OWN FORCES: 75% SUPERINTENDENT: Jim Savage CONTACT: Available upon request PROJECT DELIVERY METHOD: Design/Build
|
|
PROJECT: Madison Medical Care Development LOCATION: Madison, Maine TYPE: New construction OWNER: Madison Medical Care Development ARCHITECT: Lassell Architects CONTRACT AMOUNT: 440,202 START DATE OF PROJECT: July 2003 SCHEDULE OF COMPLETION: December 2003 PERCENT WORK WITH OWN FORCES: 50% SUPERINTENDENT: Tony Savage CONTACT: Margaret Copelin PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: USDA Lab LOCATION: Orono, Maine TYPE: New construction OWNER: USDA ARCHITECT: Delta Engineering, PA CONTRACT AMOUNT: $223,486 START DATE OF PROJECT: July 2003 SCHEDULE OF COMPLETION: December 2003 PERCENT WORK WITH OWN FORCES: 50 % SUPERINTENDENT: Richard Beaulieu CONTACT: Available upon request PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Stillwater Commercial Building LOCATION: Bangor, Maine TYPE: New construction OWNER: Stillwater, LLC ARCHITECT: N/A CONTRACT AMOUNT: $392,197.00 START DATE OF PROJECT: May 2003 SCHEDULE OF COMPLETION: November 2003 PERCENT WORK WITH OWN FORCES: 41% SUPERINTENDENT: Richard Beaulieu CONTACT: Available upon request PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Holiday Inn Room Renovations, Phase II LOCATION: Augusta, Maine TYPE: Interior finishes upgrades OWNER: Augusta Community LLC ARCHITECT: N/A CONTRACT AMOUNT: $27,025.00 START DATE OF PROJECT: September2003 DATE OF COMPLETION: October 2003 PERCENT WORK WITH OWN FORCES: 44% SUPERINTENDENT: Stacey Morrison CONTACT: Linette Searcy 207 622-4751 PROJECT DELIVERY METHOD: Construction Management
|
|
PROJECT: Border Station Re-roofing LOCATION: Houlton, Maine TYPE: Re-roofing of existing. OWNER: General Services Administration ARCHITECT: N/A CONTRACT AMOUNT: $58,390.00 START DATE OF PROJECT: 2003 DATE OF COMPLETION: 2003 PERCENT WORK WITH OWN FORCES: 22% SUPERINTENDENT: Stacey Morrison CONTACT: Larry Albright 207-532-7852 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Monmouth Library LOCATION: Monmouth, Maine TYPE: Renovations to existing Library/Theater. OWNER: Town of Monmouth ARCHITECT: HKTA CONTRACT AMOUNT: $178,000.00 START DATE OF PROJECT: March 2003 DATE OF COMPLETION: June 2003 PERCENT WORK WITH OWN FORCES: 25% SUPERINTENDENT: Cecil Lavway CONTACT: Steve Dyer, Town Manager PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Maine Veteran’s Home Addition LOCATION: 44 Hogan Road, Bangor, Maine TYPE: Major new construction addition to existing home. OWNER: Maine Veteran’s Home ARCHITECT: SMRT CONTRACT AMOUNT: $3,160,712.00 START DATE OF PROJECT: February 2002 DATE OF COMPLETION: March 2003 PERCENT WORK WITH OWN FORCES: 22% SUPERINTENDENT: Ken Smith CONTACT: Ron Herbert, MVH 207-763-6300 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Warehouse and Distribution Center LOCATION: Route 1, Newcastle, Maine TYPE: New construction pre-engineered warehouse and corporate offices. OWNER: Renbro Inc. ARCHITECT: George Parker CONTRACT AMOUNT: $3,636,965.00 START DATE OF PROJECT: May 2002 DATE OF COMPLETION: February 2003 PERCENT WORK WITH OWN FORCES: 41% SUPERINTENDENT: Kirk Wood CONTACT: John or Bob Reny 207-563-3177 George Parker 207-563-8754 PROJECT DELIVERY METHOD: Construction Management
|
|
PROJECT: Holiday Inn Room Renovations LOCATION: Augusta, Maine TYPE: Interior finishes upgrades OWNER: Augusta Community LLC ARCHITECT: N/A CONTRACT AMOUNT: $27,025.00 START DATE OF PROJECT: March 2003 DATE OF COMPLETION: May 2003 PERCENT WORK WITH OWN FORCES: 56% SUPERINTENDENT: Stacey Morrison CONTACT: Linette Searcy 207 622-4751 PROJECT DELIVERY METHOD: Construction Management
|
PROJECT: Comfort Inn Room Renovations LOCATION: Civic Center Drive, Augusta, Maine TYPE: Interior finishes upgrades. OWNER: Augusta Civic LLC ARCHITECT: N/A CONTRACT AMOUNT: $20,215.00 START DATE OF PROJECT: October 2002 DATE OF COMPLETION: PERCENT WORK WITH OWN FORCES: 21% SUPERINTENDENT: Stacey Morrison CONTACT: Linette Searcy 207 622-4751 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Site Improvements LOCATION: Air National Guard Base, Bangor, Maine TYPE: Pavement Upgrades OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $56,803.00 START DATE OF PROJECT: Project postponed until spring DATE OF COMPLETION: PERCENT WORK WITH OWN FORCES: 10% SUPERINTENDENT: Mike Hunt CONTACT: SGT Robert Busch 207-990-7419 PROJECT DELIVERY METHOD: Bid, General Contractor |
PROJECT: Install 2-Ton HVAC LOCATION: GSA IRS ADP, Augusta, Maine TYPE: Install 2-Ton HVAC and repair walls and flooring. OWNER: General Services Administration ARCHITECT: N/A CONTRACT AMOUNT: $12,545.00 START DATE OF PROJECT: November 2002 DATE OF COMPLETION: February 2003 PERCENT WORK WITH OWN FORCES: 40% SUPERINTENDENT: Stacey Morrison CONTACT: Aline Poulin 207-622-8485 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: R12 Test Stand and JP-8 Fuel Tank LOCATION: Air National Guard Base, Bangor, Maine TYPE: Small specialty projects. OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $60,020.00 START DATE OF PROJECT: May 2002 DATE OF COMPLETION: April 2003 PERCENT WORK WITH OWN FORCES: 10% SUPERINTENDENT: Cecil Lavway CONTACT: SGT Robert Busch 207-990-7419 PROJECT DELIVERY METHOD: Bid, General Contractor |
PROJECT: Repair Fuel Line Sumps LOCATION: Air National Guard Base, Bangor, Maine TYPE: Mechanical systems upgrades. OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $155,586.00 START DATE OF PROJECT: October 2002 DATE OF COMPLETION: March 2003 PERCENT WORK WITH OWN FORCES: 10% SUPERINTENDENT: Mike Hunt CONTACT: SGT Robert Busch 207-990-7419 PROJECT DELIVERY METHOD: Bid, General Contractor |
|
PROJECT: Install Perimeter Fencing LOCATION: Air National Guard Base, Bangor, Maine TYPE: Security upgrade. OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $133,902.00 START DATE OF PROJECT: October 2002 DATE OF COMPLETION: Spring 2003 PERCENT WORK WITH OWN FORCES: 10% SUPERINTENDENT: Mike Hunt CONTACT: SGT Robert Busch 207-990-7419 PROJECT DELIVERY METHOD: Bid, General Contractor |
PROJECT: Orthopaedics Associates, Tenant Fit-up LOCATION: U. S. Route 1, Scarborough, Maine TYPE: Interior tenant fit-up OWNER: Orthopaedic Associates ARCHITECT: Studio MNEMOSYNE CONTRACT AMOUNT: $157,000.00 START DATE OF PROJECT: December, 2002 DATE OF COMPLETION: PERCENT WORK WITH OWN FORCES: 5% SUPERINTENDENT: Richard Beaulieu CONTACT: Mark McAuliffe, Orthopaedics Associates, 207–828-2124 PROJECT DELIVERY METHOD: Design/Build
|
|
PROJECT: Roof Replacement Buildings 491, 493, 494, 497 LOCATION: Air National Guard Base, Bangor, Maine TYPE: Roofing upgrades. OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $289,920.00 START DATE OF PROJECT: October 2002 DATE OF COMPLETION: PERCENT WORK WITH OWN FORCES: 10% SUPERINTENDENT: Mike Hunt CONTACT: SGT Robert Busch 207-990-7419 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Carpet Replacement Building 417 LOCATION: Air National Guard Base, Bangor, Maine TYPE: Interior finishes upgrades. OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $39,000.00 START DATE OF PROJECT: October 2002 DATE OF COMPLETION: PERCENT WORK WITH OWN FORCES: 10% SUPERINTENDENT: Mike Hunt CONTACT: SGT Robert Busch 207-990-7419 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Comfort Inn Room Renovations LOCATION: Civic Center Drive, Augusta, Maine TYPE: Interior finishes upgrades. OWNER: Augusta Civic LLC ARCHITECT: N/A CONTRACT AMOUNT: $20,215.00 START DATE OF PROJECT: October 2002 DATE OF COMPLETION: PERCENT WORK WITH OWN FORCES: 21% SUPERINTENDENT: Stacey Morrison CONTACT: Linette Searcy 207 622-4751 PROJECT DELIVERY METHOD: Construction Management
|
PROJECT: Pejepscot Housing Addition LOCATION: Jordan Avenue, Brunswick, Maine TYPE: Major two-story addition to elderly housing complex. OWNER: Pejepscot Housing Authority ARCHITECT: Weinrich & Burt CONTRACT AMOUNT: $894,772.00 DATE OF COMPLETION: December 2002 PERCENT WORK WITH OWN FORCES: 48% SUPERINTENDENT: Randy Crawford CONTACT: John Weinrich 207-563-3911 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: CV Finer Foods LOCATION: Auburn, Maine TYPE: New pre-engineered building OWNER: Angustora/World Harbors ARCHITECT: Stephan Blatt Architects CONTRACT AMOUNT: $1,719,546.00 START DATE OF PROJECT: July 2001 DATE OF COMPLETION: February 2002 PERCENT WORK WITH OWN FORCES: 50% SUPERINTENDENT: John Kohler CONTACT: Mike Chestnut, Stephen Blatt Architects 207-761-5911 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Maine Machine Products Addition LOCATION: South Paris, Maine TYPE: New construction addition OWNER: Maine Machine Products ARCHITECT: SMRT CONTRACT AMOUNT: $2,092,081.00 START DATE OF PROJECT: May 2001 DATE OF COMPLETION: February 2002 PERCENT WORK WITH OWN FORCES: 65% SUPERINTENDENT: Kirk Wood CONTACT: Dave Sutton 207-743-6344 PROJECT DELIVERY METHOD: Construction Management
|
|
PROJECT: Holiday Inn Room Renovations LOCATION: Augusta, Maine TYPE: Interior finishes upgrades OWNER: Augusta Community LLC ARCHITECT: N/A CONTRACT AMOUNT: $29,480.00 START DATE OF PROJECT: August 2002 DATE OF COMPLETION: October 2002 PERCENT WORK WITH OWN FORCES: 46% SUPERINTENDENT: Stacey Morrison CONTACT: Linette Searcy 207 622-4751 PROJECT DELIVERY METHOD: Construction Management
|
PROJECT: Maintenance Building Addition LOCATION: State Street, Augusta, Maine TYPE: New construction building OWNER: Augusta Sanitary District ARCHITECT: Augusta Sanitary District CONTRACT AMOUNT: $76,626.00 START DATE OF PROJECT: April 2002 DATE OF COMPLETION: July 2002 PERCENT WORK WITH OWN FORCES: 81% SUPERINTENDENT: Tony Savage CONTACT: Harold Wood 622-6184 PROJECT DELIVERY METHOD: Construction Management
|
|
PROJECT: Clean and Upgrade Building 416 LOCATION: Air National Guard Base, Bangor, Maine TYPE: Renovations OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $77,027.00 START DATE OF PROJECT: May 2002 DATE OF COMPLETION: September 2002 PERCENT WORK WITH OWN FORCES: 32% SUPERINTENDENT: Cecil Lavway CONTACT: MSGT James Winchenbach 207-990-7310 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Renovate Building 510 for Star Base LOCATION: Air National Guard Base, Bangor, Maine TYPE: Renovations OWNER: Air National Guard, Bangor ARCHITECT: Maine Air National Guard CONTRACT AMOUNT: $59,203.00 START DATE OF PROJECT: May 2002 DATE OF COMPLETION: July 2002 PERCENT WORK WITH OWN FORCES: 32% SUPERINTENDENT: Cecil Lavway CONTACT: Glen Tompkins 207-990-7461 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: US Postal Facility Alterations LOCATION: Augusta, Maine TYPE: Renovations OWNER: General Services Administration ARCHITECT: US Postal Service CONTRACT AMOUNT: $131,682 START DATE OF PROJECT: August 2001 DATE OF COMPLETION: September 2001 PERCENT WORK WITH OWN FORCES: 30% SUPERINTENDENT: Gerry Bouchard CONTACT: Aline Poulin 207-622-8485 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Grinder Room Addition LOCATION: Guilford, Maine TYPE: New construction addition OWNER: Guilford of Maine ARCHITECT: Guilford of Maine CONTRACT AMOUNT: $ 332,622 START DATE OF PROJECT: April 2001 DATE OF COMPLETION: July 2001 PERCENT WORK WITH OWN FORCES: 70% SUPERINTENDENT: Kirk Wood CONTACT: David Walker 876-3331 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Winslow VFW LOCATION: Winslow, Maine TYPE: New construction building OWNER: Macrillis-Rousseau VFW, Post #835 ARCHITECT: owner CONTRACT AMOUNT: $ 258,064.00 START DATE OF PROJECT: June 2001 DATE OF COMPLETION: August 2001 PERCENT WORK WITH OWN FORCES: 60% SUPERINTENDENT: Randy Crawford CONTACT: Walter Keisow 238-7549 PROJECT DELIVERY METHOD: Construction Management
|
PROJECT: Darling Marine Center LOCATION: Walpole, Maine TYPE: New construction building OWNER: University of Maine ARCHITECT: Weinrich and Burt CONTRACT AMOUNT: $ 2,047,192 START DATE OF PROJECT: November 2000 DATE OF COMPLETION: August 2001 PERCENT WORK WITH OWN FORCES: 60% SUPERINTENDENT: Ken Smith CONTACT: Dave Trefethen 207-581-2675 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: USDA Conference Room Addition LOCATION: Orono, Maine TYPE: New construction addition OWNER: USDA ARCHITECT: Delta Engineering CONTRACT AMOUNT: $236,498.00 START DATE OF PROJECT: September 2001 DATE OF COMPLETION: May 2002 PERCENT WORK WITH OWN FORCES: 35% SUPERINTENDENT: Randy Crawford CONTACT: Dave Torry 207-581-3372 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: Tennis Facility Addition LOCATION: Damariscotta, Maine TYPE: New pre-engineered building OWNER: CLC YMCA ARCHITECT: Coffin Engineering CONTRACT AMOUNT: $477,271.00 START DATE OF PROJECT: October 2000 DATE OF COMPLETION: February 2001 PERCENT WORK WITH OWN FORCES: 70% SUPERINTENDENT: Kirk Wood CONTACT: Barry Costa PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Lutheran Church LOCATION: Waterville, Maine TYPE: New construction OWNER: Lutheran Church of the Resurrection ARCHITECT: Lewis and Malm CONTRACT AMOUNT: $274,903.00 START DATE OF PROJECT: August 2000 DATE OF COMPLETION: December 2000 PERCENT WORK WITH OWN FORCES: 40% SUPERINTENDENT: Thom Leveque CONTACT: Brian Watson PROJECT DELIVERY METHOD: Bid, General Contractor |
PROJECT: Renovation for Museum LOCATION: Bangor, Maine TYPE: Renovation OWNER: Eastern Maine Children’s Museum ARCHITECT: Lewis and Malm CONTRACT AMOUNT: $1,288,900 START DATE OF PROJECT: May 2000 DATE OF COMPLETION: January 2001 PERCENT WORK WITH OWN FORCES: 35% SUPERINTENDENT: Randy Crawford CONTACT: Joann Welhelm PROJECT DELIVERY METHOD: Bid, General Contractor |
|
PROJECT: IRS Renovations, Muskie Building LOCATION: Western Avenue, Augusta, Maine TYPE: Renovations OWNER: General Services Administration ARCHITECT: IRS CONTRACT AMOUNT: $81,740.00 START DATE OF PROJECT: August 2000 DATE OF COMPLETION: August 2000 PERCENT WORK WITH OWN FORCES: 45% SUPERINTENDENT: Ken Smith CONTACT: Aline Poulin 207-622-8485 PROJECT DELIVERY METHOD: Bid, General Contractor |
PROJECT: Main Plant Roof Framing LOCATION: Belfast, Maine TYPE: Roof framing OWNER: Penobscot Frozen Foods ARCHITECT: None CONTRACT AMOUNT: $156,600 START DATE OF PROJECT: May 2000 DATE OF COMPLETION: August 2000 PERCENT WORK WITH OWN FORCES: 100% SUPERINTENDENT: Kirk Wood CONTACT: Bruce Starrett 800-435-4456 PROJECT DELIVERY METHOD: Bid, General Contractor
|
|
PROJECT: Bldg 489 & 491 Renovations LOCATION: Air National Guard Base, Bangor, Maine TYPE: Renovations OWNER: Maine Air National Guard ARCHITECT: Harriman Associates CONTRACT AMOUNT: $797,665.00 START DATE OF PROJECT: November 1999 DATE OF COMPLETION: April 2000 PERCENT WORK WITH OWN FORCES: 35% SUPERINTENDENT: Kirk Wood CONTACT: TSGT Annette Sullivan 207-990-7353 PROJECT DELIVERY METHOD: Bid, General Contractor
|
PROJECT: The Senator Inn LOCATION: Western Avenue, Augusta, Maine TYPE: Major new construction addition OWNER: Vern and Betsy Cook ARCHITECT: Fuller Nichols Architects CONTRACT AMOUNT: $1,935,540 START DATE OF PROJECT: February 2000 DATE OF COMPLETION: November 2000 PERCENT WORK WITH OWN FORCES: 50% SUPERINTENDENT: Ken Smith CONTACT: Vern Cook 207-622-8800 PROJECT DELIVERY METHOD: Bid, General Contractor
|